Construction Projects

Clague Park Tennis Court Improvements


The City has hired Vasco Sports Contractors, to improve the tennis courts at Clague Park. Vasco Sports contractors will start on Monday, September 19, 2016 by demolishing bad surface, crack sealing damaged areas and resurfacing all four courts. All tennis equipment will be replaced, including the tennis post and nets. Also within their scope of work is the installation of a backboard and seal coating the new court surface. This should be an amazing facelift in these old courts. Project completion is anticipated for the end of Fall 2016.

Canterbury and Detroit Road Intersection Widening


The City of Westlake has hired Mr. Excavator, Inc. to widen Detroit Rd into five lanes and Canterbury Rd into three lanes, at their intersection. The contractor has completed the waterline replacement, sanitary and storm sewer repairs which included the catch basins, along with the intermediate coarse of asphalt on the east side of Canterbury Rd south of Detroit Rd. Mr. Excavator is currently working on pouring the concrete base  on the south side of Detroit Rd east of Canterbury Rd. The new three lane roadway will consist of two through lanes in each direction and a center turn lane.  Starting the first week of September 2016, the traffic pattern will be flipped to the south side of road in order to complete the roadway rehabilitation on the north side. Project completion is anticipated to be in November 2016 with the final task of traffic signal installation.

2016 Waterline Replacement and Roadway Rehabilitation on Bradley Rd (Center Ridge Rd to Hilliard Blvd)


The City of Westlake has contracted with DiGioia Suburban Excavating, LLC. to perform the installation of a new 12 inch water main complete with new fire hydrants and valve service connections. Included with this program will be the rehabilitation of the entire roadway along with various storm and sanitary sewer point repairs. The contractor has begun to install service connections to individual houses, during this time we ask that only local traffic travel on Bradley Rd. The roadway construction will begin in late September. The project completion is scheduled for late October.

2016 Concrete Pavement Rehabilitation with Asphalt Overlay and Catch Basin Rehab on Various Streets


The City of Westlake hired  Chagrin Valley Paving, Inc. to perform pavement rehabilitation on Balmoral and Carriage Park Subdivisions. The improvements to these subdivisions involved the milling of the existing asphalt pavement, and repair of  damaged concrete pavement, and drainage structures. After concrete was repaired Chagrin Valley Paving installed a asphalt overlay to the entire area. Project is substantially completed except for punch-list items. This years contract also included miscellaneous catch basin and concrete repairs to about 100 structures through out the City. Chagrin Valley Paving Subcontracted that work out to A& J Cement and they completed repairing all of the 98 basins. 


2016 Asphalt Pavement Rehabilitation with Asphalt Overlay on Various Streets


The City of Westlake hired Specialized Construction Inc. to preform pavement rehabilitation on Schwartz Rd and Walter Rd. These repairs included fixing damaged pavement and drainage structures along with a full depth asphalt overlay to the entire roadway, with a new thickened edge to slightly widen the roadway.

Detroit Rd Resurfacing, CUY-254, PID#:95891


The City of Westlake in conjunction with the Ohio Department of Transportation have joined into a federally funded contract with The Shelly Company This contract consisted of the removal and replacement of the top 3 inches of asphalt on Detroit Rd (Corp Line to Corp Line). Shelly Co and their subcontractors, repaired catch basins, curb and handicap ramp repairs and the restriping of the roadway to meet federal standards. This project has been completed since the end of August 2016.