Construction Projects

MoveOverBanner
Ohio’s Move Over Law requires motorists to cautiously shift over one lane — or slow down if changing lanes is not possible — when passing any vehicle with flashing lights on the side of a road. Its purpose is to protect everyone who works on our roads and everyone who travels on them.​  Browse ODOT Move Over page to learn more.​ 

Wakefield Lane Water Circulation Easement

The City of Westlake hired KMU Trucking and Excavating to replace approximately 650’ of the 8 inch water circulation easement connecting Center Ridge Road to Wakefield Lane to maintain pressures and reliability in the area. Also included in the project was minor re-grading to improve an existing drainage ditch abutting the Westlake Recreation Center property. The project's bid opening was on August 31, 2017 to view the Bid Tabulations click the hyperlink.  

​2017 Sidewalk Repair Program 


On July 6, 2017 the City entered into a contract with A&J Cement to replace various sidewalk slabs through out the eastern side of the City. A&J Cement is currently working in the northeastern section of the City, Columbia Rd east to Rocky River south of  I-90 to the north side of Hilliard Blvd. Once this area is completed they will move south east. 
If you were in violation of the City Code you will see a pink "X" on the walks abutting your property and would of receive notice by mail of your inspection. To view our electronic mapping system of violated sidewalks please click here. To find out more information on your Sidewalk Survey please click the blue dot, and a pop up menu will open with data and picture links. 

Update: Project bid opening was on July 6, 2017, and contract has been awarded to A& J Cement, view the Bid Tabulations

Columbia Road Resurfacing CUY- SR-252

The City of Westlake, North Olmsted and ODOT have contract a bid for Columbia Rd (SR-252) consisting of 1.3 miles of the removal and replacement of the top 3 inches of asphalt. Also, included was catch basin, curb and handicap ramp repair and restriping the roadway to meet federal standards. This project had 80% federal funding, view Bid Tabulations 


Update: Contract was awarded to Barbicas Construction Co, Inc. Work is substantially completed, with minor punch-list items to be completed. 

Columbia Road Interchange CUY-90-3.56 (I-90/SR-252 Interchange) PID 88665


The City welcomed the opportunity to partner with ODOT to achieve a common goal of providing and maintaining a safer and more efficient transportation network. On this $4,438,971.00 project ODOT is taking the lead role and will be over seeing Terrace Construction during the next few months while they improve the southern portion of IR-90 and Columbia Road interchange. It will be configured as a diamond shape to improve intersection spacing between the interstate ramps and Detroit Road. Project completion is scheduled for the end of October 2017. 
 
Update: The new eastbound I-90 entrance ramp from Columbia Rd. is now open! This new entrance ramp onto eastbound I-90 will be used by both north and south bound Columbia traffic. The old entrance ramp to I-90 eastbound is closed permanently and is currently being demolished. 

For more details please contact ODOT District 12 by phone 216-584-2005 or email 

  1. 1
  2. 2

Dover Ditch Stream Restoration Project


The City of Westlake has awarded Mr. Excavator, Inc. the above referenced project. The site work for this project will include the realignment of the existing Dover Ditch to extend its total length and to follow a more serpentine alignment.  These improvements will enhance the existing lesser-defined drainage ditches transforming the area into a riparian corridor with fore bays, settling ponds, shallow wetlands, wetland floodplains and native plantings, transforming them into natural habitats to promote biodiversity that will improve the quality of storm water runoff in the area. Please take a look at our drone video  and our Power Point Presentation of the improvement area. The tree clearing will be preformed early spring so we not disturb the Indiana Bats (Myotis sodalis). View the Bid Tabulations

Update: The clearing and digging for the new retention basin has been complete. Contractors are currently working on grading and vegetation. Project is on schedule and should be completed this winter. 

Please check out our article in the Cleveland Plain Dealer.
  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8

Canterbury and Center Ridge Rd Intersection Improvements


This project has been awarded to Mr. Excavator, Inc. to construct the widening Center Ridge Road to 5 lanes which will consist of two through lanes in each direction and a center turn lane. Canterbury Road will be widened to three lanes one through lane in each direction and a center turn lane. New water mains, storm sewers and traffic signals are included, along with the rehabilitation of the existing sanitary sewer.This intersection will resemble the new intersection of Canterbury and Detroit Rd that was reconstructed last year. View the Bid Tabulations 


Update: Traffic has been filliped to the north side of Center Ridge Rd. When this happens Canterbury Rd between Hilliard and Center Ridge Rd will be reopened to traffic. Contractor has just completed the resurfacing of Canterbury and Center Ridge Rd. Please avoid area when possible.
  1. 1
  2. 2
  3. 3
  4. 4
  5. 5

2017 Waterline Replacement and Roadway Rehabilitation on Bradley Rd (Hilliard Blvd-Detroit Rd)


The City of Westlake will contract out a bid consisting of replacing 8,000 feet of 12 inch watermain, along with repairing sections of the existing storm and sanitary sewer. Including the rehabilitation of manholes and catch basins, followed by the removal and replacement of the top 3 inches of pavement. This project's bid opening was on April 3, 2017 and has been awarded to DiGioia-Suburban ExcavatingView Bid Tabulations

Update:
Bradley Rd is now open, this project is substantially completed except some minor punch-list items. 

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. 10
  11. 11
  12. 12
  13. 13
  14. 14
  15. 15

2017 Asphalt Pavement Rehabilitation with Asphalt Overlay on Various Streets


The City of Westlake will contract out a bid to perform pavement rehabilitation on Hall Rd (Columbia Rd to Walter Rd), Mills Rd, and the Fire Stations One and Two’s parking lot. The improvements in these areas will involve the milling of the existing asphalt pavement, repair of any remaining damaged concrete pavement, drainage structures and then provide an asphalt overlay to the entire area. In addition to the asphalt rehab this project will include stone berm repairs in various locations. This project bid opening was March 27, 2017 and was awarded to Burton ScotView Bid Tabulations 


Update:
This project is substantially completed, Punch-list items remain open. 

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6

Clague Park Pedestrian Bridge


The City has hired Nerone & Sons, Inc. to install a pre-engineered pedestrian bridge to go across Clague Dam.

In 2015 the City of Westlake’s park system was evaluated on improvements the citizens thought should occur.  One major issue, was the lack of a continues trail at Clague Park.  So this project will improve the trail system at Clague Park by linking the trail system on each side of the lake by installing a pre-engineered steel pedestrian bridge over the Dam.  
View the Bid Tabulations

. Update: The bridge has been install and contractor is currently installing all the concrete approaches. 

2017 Concrete Pavement Rehab with Asphalt Overlay and Catch Basin Rehab


The City of Westlake will contract out a bid to perform pavement rehabilitation on Hilliard Woods Subdivision, Bretton Woods SubD Ph1, Windmill Drive, and Tricia Dr. The improvements in these areas will involve the milling of the existing asphalt pavement, and repair of any remaining damaged concrete pavement, drainage structures and then provide an asphalt overlay to the entire area. Shiloh Park, Chairman’s Row, Woodmill, Lands End, Silver Ridge, Falkirk, Barclay and Dover Center will have the same process except be replaced with concrete only in various areas. Canterbury Manor Subdivision has been rehabilitated in prior years with an asphalt overlay. Now the existing concrete curbs have deteriorated to a point that they need spot replacement throughout the subdivision as well as catch basin rehabilitation. There will be a total of 150 Catch Basins repair throughout the City this year.  This project's bid opening was March 27 and has been awarded to Burton Scot, View Bid Tabulation.

Update: 
Burton Scot is currently working on finishing various catch basins through out the City.  

Fire Stations Generator Replacement


The replacement of the existing electrical generators at both fire stations will improve the emergency power capacity available and provide greater flexibility in the use of the facilities for a variety of potential emergency situations. The project includes a partial reconfiguration of the stations’ floorplans for optimal placement and operation of the new systems. This project's bid opening was on June 26, 2017 and has been awarded to Fowler Company.
View the Bid Tabulations

Update: Project is near completion.